Kenya's electricity consumption rose by 18.87% in FY2025/26, increasing the need for investment in generation, transmission and distribution infrastructure.

Kenya grid investment is becoming increasingly important as electricity consumption rises. The country needs to expand generation, transmission and distribution infrastructure to meet growing demand while maintaining a reliable electricity supply.
The latest annual statistics from Kenya’s Energy and Petroleum Regulatory Authority (EPRA) cover the financial year ended June 2026. They show continued growth in electricity consumption and customer connections.
Domestic electricity consumption rose by 18.87% to 4,327.07 gigawatt-hours (GWh). Meanwhile, grid-connected customers reached 10.43 million. This followed the addition of 411,710 new connections. Large commercial and industrial consumers accounted for 47.57% of total consumption, according to the EPRA 2026 Energy and Petroleum Statistics Report.
These figures highlight the infrastructure needed to support wider electricity access, industrial activity and new sources of demand. Electric mobility is also becoming an additional consideration.
Kenya grid investment faces rising electricity demand
Kenya recorded a new peak electricity demand of 2,514.28 megawatts (MW) on 29 June 2026. This was an 8.55% increase from the previous financial year.
Electricity generation also increased during the reporting period. Total generation reached 15,692.81 GWh, representing year-on-year growth of 8.44%.
By June 2026, installed generation capacity had reached 3,987.20 MW. This figure includes interconnected, captive and off-grid generation. Renewable sources accounted for 81.16% of installed capacity, according to EPRA.
The June peak exceeded the previous record of 2,439.06 MW. Kenya Power reported that earlier peak in December 2025. The utility attributed the increase to new customer connections, industrial activity and improved system efficiency.
Looking ahead, Kenya Power projected further growth in electricity demand. In August 2026, it estimated peak demand could reach approximately 2,553 MW in 2026 and 2,680 MW by 2027. The projections were based on annual growth of around 5%, according to The Star.
As demand increases, investment across the electricity supply chain becomes more important. Additional generation can help meet consumption needs. However, transmission and distribution networks must also deliver electricity to households, businesses and industrial centres.
Transmission investment becomes increasingly important
Kenya is pursuing several transmission projects to strengthen its national grid. These developments aim to improve reliability and accommodate future demand.
In December 2025, the Kenya Electricity Transmission Company (KETRACO) signed a public-private partnership agreement worth approximately US$311 million. The consortium includes Africa50 and India’s Power Grid Corporation.
The agreement covers two high-voltage transmission corridors. These are the 400-kilovolt Lessos–Loosuk line and the 220-kilovolt Kibos–Kakamega–Musaga line. The project also includes associated substations.
According to KETRACO’s announcement, the project will be privately financed and implemented.
The Lessos–Loosuk line is expected to provide an alternative route for evacuating up to 300 MW of wind power from the Lake Turkana Wind Power project. It will also support proposed geothermal generation in the North Rift.
Meanwhile, the Kibos–Kakamega–Musaga line will extend the high-voltage grid into Western Kenya. The development is intended to support regional electricity supply and reduce technical losses.
Further investment proposals have also emerged. In July 2026, KETRACO opened privately initiated proposals for public review under the public-private partnership framework.
The proposals cover transmission lines and substations serving areas including Mutomo, Voi, Taveta, Maralal and Kilgoris. Their preliminary investment estimates range from KSh50 billion to KSh65 billion.
However, these projects have not received final approval. They remain subject to technical, financial and legal evaluation, stakeholder consultation and other applicable processes. Further details appear in KETRACO’s public disclosures.
The proposals therefore represent potential investment opportunities, rather than approved infrastructure projects.
Renewable energy expansion requires stronger networks
Renewable energy accounts for a substantial share of Kenya’s installed generation capacity. Geothermal, hydropower, wind and solar resources contribute to the country’s electricity supply.
As more renewable generation capacity becomes available, transmission infrastructure will be needed to connect projects with consumption centres. Stronger networks can also improve system flexibility and reliability.
In particular, grid reinforcement can help accommodate variable sources such as wind and solar. It can also support the integration of these sources alongside more consistent geothermal generation.
KETRACO’s transmission portfolio includes grid reinforcement and regional interconnection developments. Together, these investments form part of the infrastructure needed to connect generation projects to the national network.
Electricity investment and Kenya’s energy transition
Electric mobility is another emerging source of electricity demand. EPRA’s latest statistics show that consumption in the electric mobility category increased by 143.01% during FY2025/26.
Consumption rose from 5.04 GWh to 12.25 GWh. Although electric mobility remains a small share of national electricity consumption, its growth adds to future network planning requirements.
Kenya grid investment is becoming increasingly important as rising electricity demand creates new requirements across the power supply chain.
Consequently, coordinating these investments with renewable energy development will be important. This will help Kenya accommodate future demand while maintaining reliable electricity supply and supporting its energy transition.